PERT / CPM network

Activities as a dependency network with durations — the critical path read off the longest chain.

pert.cpm@1New DDN source
Open viewerOpen designerRun verifierDownload DDN

Why use it?

Schedule risk lives on the critical path; the network makes "what slips the date" a computable question.

When it helps

Project planning where dependencies, not calendars, drive the end date.

How to read it

What you need

Things to check

Scope of this diagram

Declared network; path arithmetic follows the declared durations, estimation method is yours to document.

Work with the converted example

  1. Open the viewer and select plan. Inspect the rendered view and its source.
  2. Open the designer. Keep the selected profile and inspect its legal palette and property controls.
  3. Change one displayed title or an appropriate data value. Apply the edit and check the resulting diagram.
  4. Run the verifier and review its diagnostics before moving complete content into review.
  5. Download your edited DDN source to retain the change.

The example uses the indentation-based ddn-next-1 dialect. The language guide explains reusable definitions, dotted data rows and explicit property blocks.